Principles: carry out the designing and implement of the “third party” which influence the installation and debugging of this project as soon as possible. For example: integrated wiring, power supplying and distribution system, decoration, for the purpose of supplying transporting media and reliable power supply for the debugging of other systems, and for the purpose of shortening the time limit of installation, so that sufficient time can be left for the debugging of the sub-system and general system and the reliability of the system can be insured.
Designing: tasks like purchase of equipment and preparation of construction must be carried out rapidly after the signing of the contract. Main managers and technical staffs of the Department of Project Manager must be present at the locale; and according to the process of the project decided by the owner, complete the SECURITY SYSTEM information exit, power switch/exit blueprints, linking charts of the system, basic charts of equipment installation, layout charts machine rooms and other construction charts and re-designing of the system, and then start working after the examination and approval of the owner.
Construction team enters the locale rapidly: builders and construction equipments must enter the locale and complete the preparative works.
Cooperation: every requirements and instructions must be understood and executed as quickly as possible, and cooperation must be made with the user of the construction locale through the owner or present engineer.
Purchase of equipment: project manager must make the material schedule available to ensure the working fluent and efficient.
Equipment installation: outfield equipments installation shall be started right after the equipments enter the locale. For the interests of the third party, basic check shall be done first before the installation. The equipments shall be installed according to the process decided by the owner and the installed equipments shall be well maintained.
Process control: weekly/monthly process schedules must be made and delivered to the owner for examination and approval. It must be ensured to complete these schedules.
Lag of construction behind the schedules: when actual construction process lags behind the schedules, emergency schedules shall be carried out to make up the lag. Main measures of the emergency schedules include: rapidly transferring sufficient technical staffs into the locale, adding enough working machines and tools, increasing working areas. And under the preconditions of being approved by the owner, ensuring the safety of working and quality of the construction, multi-area-working and cross-area-working also may be carried out to make up the lag.
Construction process schedule: Attachment
Principles of quality management and control: anything must be answered for by somebody, anything must be subject to available rules, anything can be checked, and anything must be supervised by somebody available.
Followings are the duties and requirements of project managers for quality management:
(1)Taking charge of formulating quality guidelines and objects and making them into written forms, and ensuring that all levels of staffs understand and stick to the guidelines.
(2)Being responsible for the work relating to “organization ”; Deciding the organizing structure and distributing their functions; regulating the duties, extents of authorities and interrelations of organizations and quality-relating staffs; deciding and outfitting sources need for the operation of the enterprise responsible for the projects, including materials, financial source and staff source; appointing quality controlling representatives and defining their duties and extents of authorities.
(3)Taking charge of management judgment, approving procedure files of management judgment, and judging the quality system on schedule to ensure the suitability and effectiveness of the system.
Department of Project Managers answers for technical coordination and judgment, defining the owner’s requirement to reach a consistent understanding and explanation of the contract between the two sides; records of the judgments shall be well kept. If necessary, the above contents may be modified in accordance with the stipulated procedure, and the modified contents must be delivered to the relating department of our company in time.
Technical and construction data of the project are important basis of project quality and working quality, so an all-way record must be kept from the phase of construction preparation, and the phase of construction organization, to the phase of hand-over and checking before acceptance of the project; anything must have record for checking, providing important basis for future maintaining, checking, rebuilding, extending and renewing of the project.
Considering the characteristics of the system, the archiving of the software documents shall be specially emphasized.
Project managers and professional workers must work out monthly and ten-day material plan according to the material analyzing sheets, and make the materials enter into the locale in advance.
Producers’ certificates of quality of all materials of every system to enter the locale must be available. Quality and properties of materials must be in accordance with relating state standards and requirements of designation.
Strictly adhering to the owner’s requirements on construction management, organizing the construction harmoniously, transacting procedures of entering the locale.
Making technical staffs accept training on installation instructions, judgment standards and main contents of the quality system.
Carrying out installation strictly in accordance with state regulations and standards and relating techniques.
Doing cleaning and maintaining works to the installed equipments.
Through marking of products and construction, ensuring that products and system communications used in the project have recognizable marks and records and can be traced back.
Marking of products includes names, specs, producers, date of entering the locale, status of inspection and test.
Workers for every sub-project shall do the work of marking during the process of installation.
When the contract/system of construction need to be traced back, it can be traced back through checking the locale construction log, ulterior check-and-acceptance sheet of the project, quality certificates of used materials, storage sheet, marking tag, judgment record of quality check-and-acceptance.
Because this project is a systems engineering, the fluent implementation of the project closely depends on the active cooperation and coordination of all sides. The Department of Project Managers of our company will establish relating principles and ways on coordination to ensure a smooth channel, an in-time responding and a high efficiency.
Basic measures of coordinating and organizing:
1. Coordinating records being established on the company’s organizing level, and special person being available for it.
2. Coordinating records being established in the locale Department of Project Managers, and special person being available for it.
3. Coordinating levels being established for in-time coordination.
4. Participating relating meetings on projects.
5. Calling on multilateral coordinating conference if necessary.
6. The decision of coordinating being implemented rapidly.
Minimizing the change during the process of construction. Main methods as below:
1、 Thoroughly and unmistakably understanding the requirements of the project, and keeping enough communications with the owner and the user, ensuring the harmony of designing and requirements.
2、 Fully considering the compatibility, conveniency and expansibility of the designing of the system.
3、 When change being inevitable, alteration documents must be formed rapidly, of which the contents include the changed items, causes for changing, measures of changing and its workload.
4、 The two sides on consultation may decide the limit of the cost for the change. For example, cost below RMB5000 for single change being born by the contractor, and cost above RMB5000 for single change being compensated by the owner.
The tenderer has the responsibility to the lab simulative testing, installation, debugging, on-the-spot inspection, pilot operation and other works, until being checked and accepted by the owner.
This tenderer will provide a detailed schedule including lab simulative testing, general installation, on-the-spot inspection, system testing and pilot operation to the owner, and implement it after being approved by the owner.
According to the owner’s examining and approving procedure, this tenderer will provide staff and organization structure for the project along with the resume of relating staffs (including name, nationality, age, installation or operation certificate, technical level certificate and other certificates.). If a staff is considered disqualified by the owner, this tenderer will immediately change that staff according to the requirement of the owner.
Construction workers in the locale shabbily must obey the management of the owner, abide with the safety regulations, pay attention to safety in production and using power and fireproofing, strive for civilized construction.
All system software and equipments listed in this spec instruction shall be installed, cleaned and maintained by this tenderer until the owner signs a certificate of check and acceptance.
system consists hardware and relating software. Hardware includes: server of the system, working stations and kinds of displays. All of these equipments are precise and expensive electric instruments, therefore high standards of protecting measure are necessary. System software includes: database, operating system, kinds of internet applications, kinds of software for connection, etc. The installation of system software is the key to the normal use and operation of the whole system. As a professional integrator of light current system, this tenderer has rich experience on installation and debugging of airport light current system. Also, we have practices of providing system for several big airports. Therefore, we are competent for the system of Guangzhou XinBaiYun airport. The installation of the hardware of this system can be divided into the following steps:
ü This tenderer will actively cooperate with civil construction unit and decoration unit to ensure the fluent development of the installation.
The equipments are all packed with standardized package according to the requirement. After reaching the NEW BAIYUN airport, all equipments will be stored and maintained as a whole. The concept that equipments reaching the locale during the process of installation mean equipments being transported from storage to the spot of installation. When the equipments enter the waiting-room building, it shall be careful to protect the decorated floor.
After installation, the equipments shall be cleaned, and the the screen shall be protected. As to equipments, if they are on a people-crowded spot that collision is liable to happen, their the screen shall be covered with cardboard.
After the installation of the equipments of system, it’s necessary to connect the electric wires and signal cables. To ensure normal power supply and communication, this integrator will send professional staffs to complete the above-mentioned work.